Update: March 23, 2015

The base for the track is down, all the drain tile is in, the earth moving is all done and we are on schedule to pour concrete at the end of April if mother nature co-operates and have a ”soft” opening of June or July if (again) the weather is good. Stay tuned, we will update as we move forward.
Thank You
Team 42